by Izabela Ryterska-Stolpe | Dec 23, 2024 | renovations
December 19, 2024, Disaster, We are Short of Tiles! Today the conservator’s inspection is taking place, and we are missing 4 square meters of tiles… A very nervous atmosphere at the construction site of the chapel. Our contractor went out of his...
by sowiweb1 | Nov 24, 2024 | renovations
December 13, 2024, Roof at the End! The fact that we were quiet, does not mean nothing was happening at the Cha-pel… We wrote letters and learned how to work with a conservator. It’s not easy. Our application for windows on both sides of the roof...
by sowiweb1 | Oct 28, 2024 | renovations
October 22, 2024 Dismantling the Table at the Former Altar Dismantling the table at the former altar turned out to be quite a task. And what looked relatively easy turned out to be a huge job. The table was a brick structure that someone planned to use for...
by sowiweb1 | Oct 25, 2024 | renovations
September 15, 2024 Flood in the Kłodzko Valley and the condition of Ka-Plica The flood disaster in the Kłodzko Valley fortunately bypassed Kudowa Zdrój and our Ka-Plica survived without any flooding. Several holes in the roof sheathing were removed in time...
by sowiweb1 | Oct 25, 2024 | renovations
May 20, 2024, Starting the Renovations The wheels of renovation have been set in motion… and we started by assessing the things that needed to be done first. Upgrading the security system seemed important, and the roof grant, due by December 2024, was the...