by iza_2025 | Mar 5, 2025 | renovations
March 3, 2025 Beetroot-Brown, how to get rid of it? We are waiting for spring… But in the meantime we tired to outsource a few small jobs. We have some beautiful wooden doors to the sacristy, and like everything else, they were painted in this terrible...
by iza_2025 | Jan 30, 2025 | renovations
January 25, 2025 Roof Finished - Grant Sign Up! The board about the subsidy stands proudly by our Ka-Plica. While we were putting it up, tourists were peeping in to the chapel in large numbers, asking what was going on and when we were opening. Their really...
by Izabela Ryterska-Stolpe | Dec 23, 2024 | renovations
December 19, 2024, Disaster, We are Short of Tiles! Today the conservator’s inspection is taking place, and we are missing 4 square meters of tiles… A very nervous atmosphere at the construction site of the chapel. Our contractor went out of his...
by sowiweb1 | Nov 24, 2024 | renovations
December 13, 2024, Roof at the End! The fact that we were quiet, does not mean nothing was happening at the Cha-pel… We wrote letters and learned how to work with a conservator. It’s not easy. Our application for windows on both sides of the roof...
by sowiweb1 | Nov 18, 2024 | renovations
November 14, 2024 Entrances for Ants and -3C on the Roof Like almost every week on Friday, it’s time for the news from Ka-Plica. Winter has come, -3C on the roof this morning, and our brave team, after warming sausages for breakfast, continues working...
by sowiweb1 | Nov 17, 2024 | renovations
October 24, 2024 A Very Important Meeting Some very important people visited us today… Today, the inspector from the Provincial Conservator of Monuments discussed with the construction manager, inspector and roof contractor the individual stages of roof...