by iza_2025 | May 3, 2025 | renovations
April 3, 2025, We begin Stratigraphic Research Stratigraphic studies… what is that? According to the current requirements, in order to receive the desired renovation permit from the conservator of monuments, we have to conduct so-called...
by iza_2025 | Jan 30, 2025 | renovations
January 25, 2025 Roof Finished - Grant Sign Off! The board about the subsidy stands proudly by our Ka-Plica. While we were putting it up, tourists were peeping in to the chapel in large numbers, asking what was going on and when we were opening. Their really...
by Izabela Ryterska-Stolpe | Dec 23, 2024 | renovations
December 19, 2024, Disaster, We are Short of Tiles! Today the conservator’s inspection is taking place, and we are missing 4 square meters of tiles… A very nervous atmosphere at the construction site of the chapel. Our contractor went out of his...
by sowiweb1 | Nov 24, 2024 | renovations
December 13, 2024, Roof at the End! The fact that we were quiet, does not mean nothing was happening at the Cha-pel… We wrote letters and learned how to work with a conservator. It’s not easy. Our application for windows on both sides of the roof...
by sowiweb1 | Nov 18, 2024 | renovations
November 14, 2024 Entrances for Ants and -3C on the Roof Like almost every week on Friday, it’s time for the news from Ka-Plica. Winter has come, -3C on the roof this morning, and our brave team, after warming sausages for breakfast, continues working...