December 19, 2024, Disaster, We are Short of Tiles! Today the conservator’s inspection is taking place, and we are missing 4 square meters of tiles… A very nervous atmosphere at the construction site of the chapel. Our contractor went out of his...
by sowiweb1 | Nov 24, 2024 | renovations
December 13, 2024, Roof at the End! The fact that we were quiet, does not mean nothing was happening at the Cha-pel… We wrote letters and learned how to work with a conservator. It’s not easy. Our application for windows on both sides of the roof...
by sowiweb1 | Nov 18, 2024 | renovations
November 14, 2024 Entrances for Ants and -3C on the Roof Like almost every week on Friday, it’s time for the news from Ka-Plica. Winter has come, -3C on the roof this morning, and our brave team, after warming sausages for breakfast, continues working...
by sowiweb1 | Nov 17, 2024 | renovations
October 24, 2024 A Very Important Meeting Some very important people visited us today… Today, the inspector from the Provincial Conservator of Monuments discussed with the construction manager, inspector and roof contractor the individual stages of roof...
by sowiweb1 | Oct 28, 2024 | renovations
October 22, 2024 Dismantling the Table at the Former Altar Dismantling the table at the former altar turned out to be quite a task. And what looked relatively easy turned out to be a huge job. The table was a brick structure that someone planned to use for...
by sowiweb1 | Oct 28, 2024 | renovations
October 20, 2024 Conservation of the roof Oh, things are happening… in our Ka-Plica! After studying the documents we received from the previous owners, we decided to protect the roof truss as soon as possible with appropriate insecticides. It would be a...