by Izabela Ryterska-Stolpe | Dec 23, 2024 | renovations
December 19, 2024, Disaster, We are Short of Tiles! Today the conservator’s inspection is taking place, and we are missing 4 square meters of tiles… A very nervous atmosphere at the construction site of the chapel. Our contractor went out of his...
by sowiweb1 | Nov 18, 2024 | renovations
November 14, 2024 Entrances for Ants and -3C on the Roof Like almost every week on Friday, it’s time for the news from Ka-Plica. Winter has come, -3C on the roof this morning, and our brave team, after warming sausages for breakfast, continues working...
by sowiweb1 | Nov 17, 2024 | renovations
October 24, 2024 A Very Important Meeting Some very important people visited us today… Today, the inspector from the Provincial Conservator of Monuments discussed with the construction manager, inspector and roof contractor the individual stages of roof...
by sowiweb1 | Oct 28, 2024 | renovations
October 22, 2024 Dismantling the Table at the Former Altar Dismantling the table at the former altar turned out to be quite a task. And what looked relatively easy turned out to be a huge job. The table was a brick structure that someone planned to use for...
by sowiweb1 | Oct 25, 2024 | renovations
September 15, 2024 Flood in the Kłodzko Valley and the condition of Ka-Plica The flood disaster in the Kłodzko Valley fortunately bypassed Kudowa Zdrój and our Ka-Plica survived without any flooding. Several holes in the roof sheathing were removed in time...