Renovations

October 15, 2025 The Main door is Going for Renovation

October 15, 2025 The Main door is Going for Renovation

It is time to send our main door for a proper face lift.So, after consulting our heritage department officer, who suggested renovating the main doors instead of installing new ones, we called in a talented team of carpenters from Bystrzyca Kłodzka to take the doors...

July 1 2025, Lightning Protection System Repair

July 1 2025, Lightning Protection System Repair

Time to repair the damaged lightning protection system...I trembled every time a storm passed over Ka-Plica. We noticed the broken lightning protection system a long time ago, but there were constantly problems getting our electrician over to repair it. So,  we had to...

April 3, 2025, We begin Stratigraphic Research

April 3, 2025, We begin Stratigraphic Research

Stratigraphic studies... what is that?According to the current requirements, in order to receive the desired renovation permit from the conservator of monuments, we have to conduct so-called 'stratigraphic research'. Without this, it will not work because we want to...

March 3, 2025 Beetroot-Brown-How to Get Rid of it?

March 3, 2025 Beetroot-Brown-How to Get Rid of it?

We are waiting for spring...But in the meantime we tired to outsource a few small jobs. We have some beautiful wooden doors to the sacristy, and like everything else, they were painted in this terrible brown-betroot color probably in the 1980s. But luckily after...

January 25, 2025 Roof Finished – Grant Sign Off!

January 25, 2025 Roof Finished – Grant Sign Off!

The board about the subsidy stands proudly by our Ka-Plica.While we were putting it up, tourists were peeping in to the chapel in large numbers, asking what was going on and when we were opening. Their really nice comments motivated us to work faster, but we cannot...

December 19, 2024, Disaster! We are Short of Tiles!

December 19, 2024, Disaster! We are Short of Tiles!

Today the conservator's inspection is taking place, and we are missing 4 square meters of tiles... A very nervous atmosphere at the construction site of the chapel. Our contractor went out of his way to bring the missing tiles from Poznań (a shy 300 km dirive), but...

December 13, 2024, Roof at the End!

December 13, 2024, Roof at the End!

The fact that we were quiet, does not mean nothing was happening at the Cha-pel...We wrote letters and learned how to work with a conservator. It's not easy. Our application for windows on both sides of the roof was rejected (as recommended by the roofer) and we have...

November 14, 2024 Entrances for Ants and -3C on the Roof

November 14, 2024 Entrances for Ants and -3C on the Roof

Like almost every week on Friday, it's time for the news from Ka-Plica.  Winter has come, -3C on the roof this morning, and our brave team, after warming sausages for breakfast, continues working on the roof. It's slippery there and I don't know how they do it without...

October 24, 2024, A Very Important Meeting

October 24, 2024, A Very Important Meeting

Some very important people visited us today...Today, the inspector from the Provincial Conservator of Monuments discussed with the construction manager, inspector and roof contractor the individual stages of roof replacement and possible installation of roof windows...