Renovations
October 24, 2024, A Very Important Meeting
Some very important people visited us today...Today, the inspector from the Provincial Conservator of Monuments discussed with the construction manager, inspector and roof contractor the individual stages of roof replacement and possible installation of roof windows...
October 22, 2024, Dismantling of the Former Altar
Dismantling the table at the former altar turned out to be quite a task.And what looked relatively easy turned out to be a huge job. The table was a brick structure that someone planned to use for something very serious. It could have carry a few tonnes of weight. The...
October 20, 2024, Conservation of the Roof Trusses
Oh, things are happening... in our Ka-Plica!After studying the documents we received from the previous owners, we decided to protect the roof truss as soon as possible with appropriate insecticides. It would be a shame if the new roof fell off, because it had nothing...
September 15, 2024, Flood in the Kłodzko Valley and Our Cha-Pel
The flood disaster in the Kłodzko Valley fortunately bypassed Kudowa Zdrój and our Ka-Plica survived without any flooding.Several holes in the roof sheathing were removed in time and the building was well protected while waiting for a new roof. In the meantime, we...
September 1, 2024 We are preparing to renovate the roof
We are preparing to renovate the roofThe long search for a company that would replace the roof by December 11, 2024, ended in success. Thanks to the subsidy obtained by the previous owner, our renovation will be cheaper by PLN 129,000. This is a significant sum and we...
July 15, 2024, Removing Graffiti from the Walls of Cha-Pel
According to the principle that my grandmother followed: "It may be poor, but it must be clean"... we began removing graffiti from the walls of Ka-Plica. My brave team approached the problem twice to choose the best method. They scraped for two whole days and slowly...
May 20, 2024, Starting the Renovations
The wheels of renovation have been set in motion…and we started by assessing the things that needed to be done first. Upgrading the security system seemed important, and the roof grant, due by December 2024, was the most urgent item on the list. We asked our architect...